Work Breakdown Structure
Project Name: District 4 Warehouse Move
Project
Manager:
Date:
Work
Breakdown Structure Purpose and Limitations
The
purpose of this worksheet is to:
Identify the work to be done

Identify the types of
resources required for the work
Develop estimates for each work element

This
worksheet does not address:
When the work will be completed
Use the following table to define
the major deliverables and associated task detail for each deliverable. Use
the example (in red) for help in determining how to break up the work and
identify the Work ID numbers. Expand the table as needed.
Work Package
Task
Tasks Resource(s)
Required
Estimated
Duration
(in days)
Tasks
Estimated
Duration
(in days)
Work Package
ID
1 Project
Kick-off
4
1.1 Book
location for meeting
Project
Manager
1
1.2 Invite
stakeholders
Project
Manager
1
1.3 Prepare
presentation
Project
Manager
1
1.4 Conduct
the meeting
Project
Manager and Attendees
1
2 Project
Documents
13
2.1 Develop
Charter/Scope
Project
Manager
2
2.2 Develop
WBS
Project
Manager and Workers
7
2.3 Develop
Project Plan
Project
Manager
2
2.4 Develop
Communication Plan
Project
Manager
2
3 Status
Reports/Meetings
3
3.1 Develop
Status Report
Project
Manager
1
3.2 Set
schedule for team meetings
Project
Manager
1
3.4 Set
schedule for stakeholder meetings
Project
Manager
1
4 Initial
Planning Meetings with Vendors
5
4.1 Meet
with Framing/Drywall
Project
Manager and East Side Framing PM
1
4.2 Meet
with Electrical
Project
Manager and Sparks Electrical PM
1
4.3 Meet
with Plumbing
Project
Manager and Waterworks Plumbing PM
1
4.4 Meet
with Finish Work
Project
Manager and Woodcraft Carpentry PM
1
4.5 Meet
with Student Workers
Project
Manager and Student Workers Manger
1
5 Electrical
Permits
10
5.1 Obtain
Electrical Permits
Sparks
Electrical PM
10
6 Plumbing
Permits
10
6.1 Obtain
Plumbing Permits
Waterworks
Plumbing PM
10
7 Building
Permits
10
7.1 Obtain
Building Permits
East
Side Framing & Drywall PM
10
8 Framing 24
8.1 Framing-Order
Supplies
East
Side Framing & Drywall PM
3
8.2 Framing-Build East
Side Framing & Drywall
15
8.3 Framing-Inspect City
& County
5
8.4 Framing-Project
Sign-off
Project Manager 1
9 Electrical 19
9.1 Electrical-Order
Supplies
Sparks
Electrical PM
3
9.2 Electrical-Install Sparks
Electrical
10
9.3 Electrical-Inspect City
& County
5
9.4 Electrical-Project
Sign-off
Project Manager 1
10 Plumbing 19
10.1 Plumbing-Order
Supplies
Waterworks
Plumbing PM
3
10.2 Plumbing-Install Waterworks Plumbing 10
10.3 Plumbing-Inspect City & County 5
10.4 Plumbing-Project
Sign-off
Project Manager 1
11 Drywall 24
11.1 Drywall-Order
Supplies
East
Side Framing & Drywall PM
3
11.2 Drywall-Install East
Side Framing & Drywall
15
11.3 Drywall-Inspect City
& County
5
11.4 Drywall-Project
Sign-off
Project Manager 1
12 Finish
Work
24
12.1 Finish-Order
Supplies
Woodcraft Carpentry
PM
3
12.2 Finish-Install Woodcraft Carpentry 15
12.3 Finish-Inspect City & County 5
12.4 Finish-Project
Sign-off
Project Manager 1
13 Workbenches 20
13.1 Workbenches-Order
Supplies
Student Workers
Manager
2
13.2 Workbenches-Build Student Workers 15
13.3 Workbenches-Quality
inspection
Project Manager 2
13.4 Workbenches-Project
Sign-off
Project Manager 1
14 Equipment
Packing
5
14.1 Pack
production equipment
City Equipment Movers
PM
2
14.2 Pack
non-production equipment
City Equipment Movers 2
14.3 Project
Sign-off
Project Manager 1
15 Move 7
15.1 Move
production equipment
Express Moving
Company PM
3
15.2 Move
non-production equipment
Express Moving
Company
3
15.3 Project
Sign-off
Project Manager 1
16 Procurement
Closure
5
16.1 Review
contract work
Project Manager 3
16.2 Release
contractors
Project Manager 1
16.3 Pay
contractors
Project Manager 1
17 Project
Closure
7
17.1 Final
report
Project Manager 3
17.2 Archive
documentation
Project Manager 3
17.3 Lessons
Learned
Project Manager 1