Yaqeen Manufacturing is thinking of using Activity based Costing system and has identifies four activities. The four activities, cost drivers, annual activity level, and expected overhead costs for each activity for next year are listed below.

Annual Cost-Driver

Activity Cost Driver Activity Level Expected FOH

Maintenance Machine hours 40,000 $300,000

Materials Handling Material moves 8,000 150,000

Setups Setups 10,000 200,000

Inspection Quality inspections 15,625 250,000

Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labor hours. 100,000 direct labor hours are budgeted for next year.

Estimates for product AS1 are as follows:

Direct materials $20,000

Direct labor (1,000 hours) $15,000

Number of materials moves 20

Number of inspections 25

Number of setups 5

Number of machine hours 750

What is the expected total cost of product AS1 if traditional cost accounting is used?What is the expected total cost of product AS1 if activity-based costing is used?