Use the table for the question(s) below.

Consider the following list of projects:

Project

Investment

NPV

A

135,000

6,000

B

200,000

30,000

C

125,000

20,000

D

150,000

2,000

E

175,000

10,000

F

75,000

10,000

G

80,000

9,000

H

200,000

20,000

I

50,000

4,000

Assuming that your capital is constrained, which project should you invest in last?

Project A
Project C
Project D
Project I