Use the following information to answer the question.

Distribution Center A
Transit Time: 1 week
Order Quantity: 200 units
Current Inventory: 75 units

Week

1

2

3

4

5

Gross Requirements

150

125

125

100

150

In Transit

200

Projected Available

Planned Order Release

There will be a planned order release(s) in weeks:

a.

2 and 3

b.

In-transit inventory will cover all the orders.

c.

1 and 2

d.

1, 2, and 3

e.

1 and 3